MAKUENI COUNTY FIRST QUARTER FY 2020-21 BUDGET IMPLEMENTATION REPORT

First Quarter Budget implementation report highlights progress made in implementation of the Makueni County Government Budget for the first three months of the Financial Year 2020/2021, for the period ending 30th st September 2020. It also presents the key challenges that faced budget implementation during the reporting period and appropriate recommendations to overcome these challenges. The FY 2020/21 annual budget estimates was Kshs. 11,446,609,852.76 which was to
be financed by projected local Revenue Collection, and Shareable revenue from National Government and conditional grants.

The total revenues mobilized in the first quarter were Kshs 805,917,647.10. The County expenditure for the 3months period amounted to Kshs. 335,495,735.95 all recurrent expenditures. The projected revenues and expenditures in the CFSP were adjusted from the printed budget estimates to capture policy changes accommodating dynamic public priorities during budget public participation fora. The Budget was the second to implement the CIDP 2018-22 and was anchored on the County Government agenda of socio economic transformation with a broad focus on community economic empowerment for increased household income.

MAKUENI COUNTY HALF-YEAR FY 2020-21 BUDGET IMPLEMENTATION REPORT

The Budget implementation report highlights progress made in implementation of the Makueni County Government Budget for the Financial Year 2020/2021, for the period ending 31 st December 2020. It also presents the key challenges that faced budget implementation during the reporting period and appropriate recommendations to overcome these challenges.

The total revenues mobilized in the first 6 months of FY 2020/21 were Kshs 3,712,112,013.38 representing 32 percent of the total budgeted revenues for the Financial Year. The overall County expenditure for the period amounted to Kshs. 3,196,094,826.85 against a Revised Budget of Kshs 11,672,939,708.37 representing an absorption rate of 27.38 percent for the first 6 months of FY 2020/2021. The recurrent expenditures were kshs 2,309,185,173.60 against a revised budget of Kshs 6,674,864,837.98 which translated to an absorption rate of 34.60 per cent. The development expenditure for the first 6 months of the FY 2020/21 were Kshs 886,909,653.25 against a revised budget of Kshs 4,998,074,870.39 representing an absorption rate of 18 percent.

MAKUENI COUNTY THIRD QUARTER FY 2020-21 BUDGET IMPLEMENTATION REPORT

The Budget implementation report highlights progress made in implementation of the Makueni County Government Budget for the Financial Year 2020/2021, for the period ending 31 st March 2021. It also presents the key challenges that faced budget implementation during the reporting period and appropriate recommendations to overcome these challenges.

The total revenues mobilized in the first 9 months of FY 2020/21 were Kshs 6,114,904,288.29 representing 63 percent of the total budgeted revenues for the Financial Year. The overall County expenditure for the period amounted to Kshs. 4,340,822,834.09 against a Revised Budget of Kshs 11,672,939,708.37 representing an absorption rate of 27.38 percent for the first 9 months of FY 2020/2021. The recurrent expenditures were kshs 2,921,044,056.04 against a revised budget of Kshs 6,674,864,837.98 which translated to an absorption rate of 37 per cent. The development expenditure for the first 9 months of the FY 2020/21 were Kshs 1,419,778,778.05 against a revised budget of Kshs 4,998,074,870.39 representing an absorption rate of 28 percent.

The Budget was the third to implement the CIDP 2018-22 and was anchored on the County Government agenda of socio economic transformation with a broad focus on community economic empowerment
for increased household income.

MAKUENI COUNTY FY 2020-21 ANNUAL BUDGET IMPLEMENTATION REPORT

The Budget implementation report highlights progress made in implementation of the Makueni County Government for the Financial Year 2020/21, ending 30 th June 2021.It also presents the key challenges that faced budget implementation during the reporting period and appropriate recommendations to overcome these challenges.

The County Government had an original budget of Kshs 11,446,609,852.76 representing 56 per cent recurrent and 44 per cent development and a revised budget of Kshs 11,705,104,318.97 representing 57 per cent recurrent and 43 per cent development. The Budget was the third to implement the CIDP 2018-22 and was anchored on the County Government agenda of socio economic transformation with a broad focus on community economic empowerment for increased household income.